Following the successful conclusion of the heating and ventilation plant installation works at 15 Adam Street, we are delighted to have now completed the final phase of the cooling plant replacement project.

The existing 500kW chiller has been replaced with a new modern equivalent. Works included road closure of The Strand, crane lifting operations, pipework & electrical modifications, and integration of the new chiller to the building management system.

Thank you and well done to all involved for a well planned and executed project.

Share this post

Our News

Other News

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.